Specifies the current projected cost of the task.
Namespace: [Project Web service]
Service reference: http://ServerName:32843/[Project Service Application GUID]/PSI/Project.svc
Web service reference: http://ServerName/ProjectServerName/_vti_bin/PSI/Project.asmx?wsdl
Syntax
'Declaration
Public Property TASK_COST As Double
Get
Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Double
value = instance.TASK_COST
instance.TASK_COST = value
public double TASK_COST { get; set; }
Property Value
Type: System.Double
Remarks
TASK_COST includes costs that have been incurred and costs planned but not yet incurred as of the current or status date.