Note
Access to this page requires authorization. You can try signing in or changing directories.
Access to this page requires authorization. You can try changing directories.
Contains the latest date that the task can start without delaying the finish of the project.
Namespace: [Project Web service]
Service reference: http://ServerName:32843/[Project Service Application GUID]/PSI/Project.svc
Web service reference: http://ServerName/ProjectServerName/_vti_bin/PSI/Project.asmx?wsdl
Syntax
'Declaration
Public Property TASK_LATE_START As DateTime
Get
Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As DateTime
value = instance.TASK_LATE_START
instance.TASK_LATE_START = value
public DateTime TASK_LATE_START { get; set; }
Property Value
Type: System.DateTime
Remarks
Read-only. TASK_LATE_START is based on the task's start date, the late start date and late finish date of predecessor tasks and successor tasks, and other constraints.