Note
Access to this page requires authorization. You can try signing in or changing directories.
Access to this page requires authorization. You can try changing directories.
Specifies the amount of time that the start date for the specified task can be delayed without delaying the project.
Namespace: [Project Web service]
Service reference: http://ServerName:32843/[Project Service Application GUID]/PSI/Project.svc
Web service reference: http://ServerName/ProjectServerName/_vti_bin/PSI/Project.asmx?wsdl
Syntax
'Declaration
Public Property TASK_START_SLACK As Integer
Get
Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Integer
value = instance.TASK_START_SLACK
instance.TASK_START_SLACK = value
public int TASK_START_SLACK { get; set; }
Property Value
Type: System.Int32
Remarks
The TASK_START_SLACK field contains the duration between the TASK_EARLY_START and TASK_LATE_START.
The duration is indicated in tenths of minutes. A value of 100 indicates 10 minutes.